• Complete gut of 150,000 SF academic building
  • Two phase project with the building split in half
  • Limestone façade removal for new exterior louvers
  • Removal of all rooftop equipment and steel dunnage
  • Removal of 700+ exterior windows w/ temporary weatherproofing
  • 150,000 SF of MEP removal and disposal, including tow large basement mechanical rooms
  • New interior & exterior openings
  • 400 induction heating unit removal